Bheri Corridor 400 kV Transmission Line Project

Technical Specifications

Province
Karnali
Location/Affected Area
Jajarkot, West Rukum, Salyan, Surkhet
Power Evacuation Capacity
2400 MW
Voltage
400 kV
Transmission Line Length
93 km
Substations
Nalgad, Maintada
Substation Capacity
160 MVA, 315 MVA
Targeted Completion
2086/87
Tentative Budget Required
160M USD
Major Hydropower Projects
Nalgad (410 MW), Bheri-1 (617 MW), Bheri-2 (256 MW)