Technical Specifications
- Province
- Bagmati
- Location/Affected Area
- Dolakha, Sindhupalchowk
- Power Evacuation Capacity
- 1240 MW
- Voltage
- 220 kV
- Transmission Line Length
- 43 km
- Substations
- Lambagar Substation, Barabishe Bay Extension
- Substation Capacity
- 315 MVA
- Targeted Completion
- 2087/88
- Tentative Budget Required
- 28.78 MUSD
- Major Hydropower Projects
- Lapche HEP (160MW), Upper Lepche HEP (52MW), Lapche Tamakoshi HEP (22MW), Jhoom HEP (56MW), Rolwaling HEP (88MW)