Technical Specifications
- Province
- Koshi
- Location/Affected Area
- Taplejung
- Power Evacuation Capacity
- 700 MW
- Voltage
- 220 kV
- Transmission Line Length
- 32 km
- Substations
- Tamor Substation, Dhungesanghu Bay Extension
- Substation Capacity
- 315 MVA
- Targeted Completion
- 2087/88
- Major Hydropower Projects
- Ghunsa Khola HEP (77.5MW), Super Tamor (66MW), Simbuwa Khola (70.3MW)